Haryana’s GCC Policy, 2026 pays back part of a captive centre’s capital spending, running costs and local payroll, and the support is higher in Gurugram’s transit oriented development zones and higher still outside Gurugram district. This guide is for leadership teams of multinational companies planning a new captive centre in the state, or expanding one already there.

PolicyHaryana Global Capability Centres (GCC) Policy, 2026
In forceFrom 27 May 2026 for five years, or until the state issues a new policy or amendment, whichever comes first.
Run byDepartment of Industries and Commerce, through the Haryana GCC Mission
Apply throughAn application to the Department of Industries and Commerce. Clearances and claim tracking run on the Invest Haryana Single Window Portal.

Who qualifies

  • Captive centres set up by a multinational or its parent, group, subsidiary or affiliate entities, serving only group entities and no unrelated clients.
  • BOT, joint venture and hybrid models count, provided the centre is captive and control rests, or will rest, with the multinational.
  • Commercial operations must begin after 1 January 2026 and within the policy period. The start date is the date of the first sale bill or invoice.
  • The unit must employ at least 100 people, on payroll or on contract with an ESI or PF number, within 3 years of starting operations.
  • Existing GCCs can claim once for expansion at the same location if the additional fixed capital investment is at least 50% of current investment, or at least 25% with a minimum of ₹125 crore, or above the Mega or Ultra Mega threshold for the location. Expansion at a different location counts as a new unit.

What you can claim

SupportWhat the state paysLimitPeriod
CAPEX support50% of eligible capital expenditure in Gurugram outside TOD zones, 65% in Gurugram TOD zones and 75% in every other district. Covers building, fit out, IT hardware and software, power backup, stamp duty and green certification, but not land.Owned space: the lower of ₹3.75 crore per 100 eligible employees or ₹100 crore, ₹125 crore or ₹150 crore by zone. Leased space: the lower of ₹2.50 crore per 100 eligible employees or ₹50 crore, ₹75 crore or ₹100 crore.10 annual instalments
OPEX support50% of eligible running costs in Gurugram outside TOD zones; 65% in TOD zones and in other districts. Covers electricity duty, lease rent (counted at 75% of rent paid, capped at 6% of the property’s value as assessed by a registered valuer), internet bandwidth and cloud charges.The lower of ₹0.75 crore per 100 eligible employees or ₹15 crore a year5, 7 or 9 years from commercial operations, by zone
Local employment subsidyWhere Haryana locals are 15% or more of the workforce: A share of each local employee’s average gross monthly salary, set by the formula 100% + 20% × (local share in % minus 15%). Confirm how the formula is applied with the department. Women, SC, Divyang, Agniveer and ex servicemen start at 120% and qualify even below the 15% mark, though the policy’s table lists Agniveers only in its heading.₹1 lakh per employee a year (₹1.2 lakh for the priority groups at 15% local share or more), with a floor of ₹48,00010 years
EPF support for HKRN recruits100% of the employer’s EPF contribution for Haryana locals hired through Haryana Kaushal Rozgar Nigam, on top of the employment subsidy12% of basic pay plus DA and retaining allowance, up to ₹25,000 per employee a year5 years
Internship stipend50% of the stipend paid to interns and apprentices on industry aligned courses with recognised Haryana institutions₹15,000 per intern a month; 50 interns a yearUp to 6 months per intern
R&D centre capital subsidy50% of the eligible capital cost of an R&D centre recognised by DSIR or CSIR₹50 crore (Ultra Mega), ₹25 crore (Mega), ₹10 crore (all others)5 annual instalments
R&D centre operating subsidy50% of research staff salaries, research consumables, publication fees and conference costs₹2 crore per centre a year5 years
Customised packageA case by case package over and above the standard support, decided by the Haryana Enterprise Promotion BoardMega and Ultra Mega projects only. The policy does not say whether the 100% cap covers the package.Set at approval

All support under this policy, together with any central government support for the same project, cannot exceed 100% of fixed capital investment. You cannot combine it with other Haryana policies for the same project, except the Haryana Progressive MSME and Exports Policy for heads not covered here, and R&D support is limited to 5 centres.

Where to set up

Location sets both the CAPEX rate and how long OPEX support runs. In Gurugram district outside Transit Oriented Development zones, you get 50% CAPEX support and 5 years of OPEX support. In the TOD zones notified by the Town and Country Planning Department, that rises to 65% and 7 years, with higher absolute caps. Any other district gets 75% CAPEX support, the highest caps of ₹150 crore for owned space and ₹100 crore for leased space, and 9 years of OPEX support.

How to apply, step by step

  1. Use the GCC desk. The Haryana GCC Mission runs a dedicated single window desk at Gurugram to help with location, regulation and approvals.
  2. Apply before you open. Submit your application to the Department of Industries and Commerce before commercial operations begin. Units that started between 1 January and 27 May 2026 had two months from notification to apply.
  3. Clear approvals on the portal. Clearances run through the Invest Haryana Single Window Portal, which also tracks how quickly incentive claims are processed.
  4. Seek a custom package if you are large. Mega and Ultra Mega projects can ask the Haryana Enterprise Promotion Board for a customised package, assessed on the state’s cost benefit model.
  5. File your claims. Half the eligible amount is released within 7 working days of your application, after a first check. The rest follows within 45 working days of the same application date, after a detailed check. Delays caused by the department carry interest at 8% a year.
  6. Claim R&D support separately. Apply within 3 years of the R&D unit starting operations, once it has DSIR or CSIR recognition.

Before you apply

  • Local employees must be verified as Haryana residents through Parivar Pehchan Patra, and no other proof is accepted.
  • Employees count towards caps only after a year of continuous employment. Staff relocated from your units outside Haryana do count.
  • Expansion units need separate GST registration and separate books, must sit on land with valid commercial or industrial CLU or in a government industrial estate or IMT, and earn the employment subsidy only on extra headcount.
  • Machinery transferred from elsewhere does not count as eligible capital expenditure.
  • The employment subsidy, HKRN EPF support and stipend support can each be claimed only once per person in their lifetime.

See what your centre could get. Our GCC incentive calculator compares Haryana with every other state using your own headcount and investment.

Read the full Haryana GCC profile for the latest announcements and centres, or start with our India GCC setup playbook.

Guides for other states

Have more information, data or an official update on Haryana, or spotted something to correct? Send it to our editors.

Last reviewed on 6 November 2026. The Haryana government sets the final incentives when it approves each project, and the policy itself can be revised.

The Narrative Republic is an independent business media platform dedicated to telling the story of foreign companies operating, investing, and growing in India. Through news, analysis, and executive insights, we explore how global businesses are shaping India’s economic future.

Reach Us

The Narrative Republic

Dedicated to one story: the narrative of foreign companies in India

For editorial inquiries, partnerships and research engagement: editorial@thenarrativerepublic.com

© 2026 The Narrative Republic.